PG&E is collaborating with developers and policy makers in order to power developments faster and help cut down the time it take a new project to be able to house residents. This includes improving turnaround time to schedule electrical connection, having centralized support, and providing interim power solutions.
The results so far include a 26% increase in the number of connections in the South Bay from 2022 to 2023. By streamlining process, they are hoping to sever 30% more customers in 2024 than 2023. For more details, head to the source link below.
Source:
SVBJ
No comments:
Post a Comment