Buena Vista Midtown Senior Apartments

Construction is now well underway for the Buena Vista apartment project in midtown. I don't believe that I have mentioned this project before. Buena Vista will have 95 units available for those that are 55-years-old and and meet income qualifications. The community will have several amenities and activity programs to serve residents, and the locations is right between Downtown and Santana Row. The project should be ready by next summer and you can see the full construction schedule below.

Thanks Mark for sending this in!


Hours of Construction

The City of San Jose has issued permit approvals for this development requiring that construction activity and deliveries occur Monday - Friday,  7 a.m. to 7 p.m. Additional notification and City approvals may be provided, for specific activities to be conducted outside of these hours such as on Saturdays.

Project Schedule & Sequencing

Construction will begin Thursday, May 9, 2013 and complete in approximately September of 2014.

Dates are approximate. For more detailed notifications and updates, sign up for Email Updates.
1.  May 9-17, 2013: Demolition
2.  May-June 2013: Mass Excavation (The process of digging the subterranean garage), with approximately 1-2 weeks of compaction, subject to change.
3.  Summer 2013: Concrete Pumps and Pouring
4.  Fall 2013: 1st Phase of Underground Utilities- Equipment in the streets and compaction
5.  September 2013 - January 2014: Framing the Building, cranes and manpower, delivery of prefabricated framing
6.  December 2013-June 2014: Finishes - Building in full swing with various trades (plumbers, electricians, drywallers, etc.)
7.  Summer 2014: 2nd Phase of Underground Utilities
8.  Summer 2014: Final touches, paving, landscaping, cleaning 

Truck Routes (Deliveries & Hauling)

All large equipment and trucks will be directed to enter from the southeast corner of the site and exit by continuing west on West San Carlos Street; they will be directed through signage not to turn north on either Buena Vista or Willard Avenues. The northern-most lane of W San Carlos Street will be closed during construction and pedestrian detours will be posted.

Closing the traffic lane adjacent to the site maximizes the "buffer" of distance between construction activity and the residences to the northwest, north, and northeast.

A roadway easement has been issued during construction allowing Fiesta Lane, adjacent to the Senior Apartment Site, to be used during construction for staging or equipment, as long as access is afforded to Townhome residents and visitors at all times.
Picture

Parking

Core Builders will instruct subcontractors arriving on site to park throughout public streets in a 2 block radius around the site in order to avoid parking inundation to any single area. The subterranean garage will be available to accommodate some construction parking when it is completed by late 2013.

Construction Informational Meeting

This meeting was held on May 2, 2013 at 6:00 p.m., and 17 attendees signed the sign-in sheet at the meeting. Download the
Agenda/Handout from the May 2 meeting below.

construction_meeting_handout_5-2-13.pdf
Download File

Contact Information

The Site Superintendent is Joel Hannagan of Core Builders. If you have questions or concerns regarding the construction of Buena Vista Midtown Senior Apartments on West San Carlos Street, please contact Joel at 408-373-0444 orjhannagan@thecorecompanies.com.

Main Point of Contact for Neighbors
Joel Hannagan, Site Superintendent: 
jhannagan@thecorecompanies.com, Cell: 408-373-0444 
Pieter Joosen – Project Manager, pjoosen@thecorecompanies.com Office Ph: (408) 293-9728 x36
Crystal Madeiros – Project Administrator, cmadeiros@thecorecompanies.com, Office Ph: (408) 293-9728 x17
Jim Feeley – Vice President of Construction, jfeeley@thecorecompanies.com, Office Phone: (408) 293-9728 x38

Mailing Address: Core General Contractor Inc.
dba CORE Builders
470 South Market Street
San Jose, CA  95113-2819