San Jose Trails update from City Trail Manager Yves Zuetty

from One Square Mile 

Popout
View San Jose Trails - Updates from Yves Zuetty in a larger map

San Jose Trails Update - May 2012

Highway 237 Bikeway Construction

Construction of the bikeway project between Zanker Road and Coyote Creek (north side) continues. Asphalt paving, striping and fencing are in place. Opening of the trail is delayed until early June as final work items are completed – installation of bollards, new wheelchair ramps and restoration of a vehicle detection loop at the nearby freeway off-ramp traffic signal. Follow “SanJoseTrails” on Twitter for notification of the trail’s reopening and get more detailed updates and photos by following the Construction Updates.

Lower Guadalupe River Trail Construction

A construction contract has been awarded and the pre-construction meeting occurred on May 23. The City will provide a project schedule and details about phasing during the week of June 4. Weekly project updates are posted on the Construction Updates link found on the Trail Program homepage: www.sjparks.org/trails.

Lower Guadalupe River Trail – Tasman Under-Crossing

A grant has been secured to elevate the under-crossing at Tasman Drive so that it is flooded less frequently from seasonal rains and tidal flows from the Bay. The project is within the limits of the larger Lower Guadalupe River Trail project, however, the City has postponed construction until after the larger trail project is completed. In this way, the 6.4 mile trail project is not subject to a possible seasonal closure that would only occur due to flooding at the under-crossing. The California Transportation Commission approved a grant extension on May 23, 2012. Work on the under-crossing is to get underway immediately after completion of the Lower Guadalupe River Trail project.

Thompson Creek Trail (Tully-Quimby)

Preparation of construction documents is on-going. PG&E has issued a permit and the City has positively identified all utilities along the trail alignment. Funding is in place to construct the 0.65 mile trail (improving the existing interim gravel surface). A schedule for construction will be provided once construction documents are completed.

Doerr Parkway

Two community meetings have occurred for Doerr Parkway project. The west San Jose project will develop a landscaped trail along a short 500' parcel currently used as a utility corridor. Design work is now underway – you’ll find conceptual drawings of the future trail posted at: http://www.sjparks.org/Trails/TrailsMeetings.asp

Los Gatos Creek Trail Under-Crossing (San Carlos Street)

The City has secured $1.6M in grant funding to prepare environmental and construction documents for the under-crossing that will span beneath the West San Carlos Street bridge, active Caltrain/Amtrak railway bridge and future High Speed Rail alignment. A Request for Qualifications was issued on May 24 to hire a design consultant for the project. A schedule will provided at a later date when the project team is hired. A conceptual image of the under-crossing is available.