BART to San Jose has advanced one step forward in the New Starts process. The Federal Transit Administration has now issued a Record of Decision (ROD) for the BART extension, which marks federal approval of the project’s environmental impact statement. The ROD only covers the initial phase between Warm Springs and Berryessa, including two new stations at Milpitas and Berryessa.
VTA seeks a $900 million federal contribution toward the $2.1 billion Berryessa extension. The ROD qualifies VTA to move forward in the process, and the next step is to execute a Full Funding Grant Agreement (FFGA) in February 2011, which would allow VTA to obtain the federal funding it needs to build the project. Construction could begin in 2012, and revenue service could commence in 2018.
*********************************